Plan for Development and Operation for Maria approved

[ 04.09.2015 ]
The Norwegian Ministry of Petroleum and Energy has approved the PDO for the Maria-field in the Norwegian Sea. Petoro tok over a 30 per cent share in 2011 and has in the planning phase been keen to see an efficient use of existing infrastructure as part of the Maria field development in this part of the Norwegian Sea.
Investments in the Maria development are estimated at around 15.3 billion NOK including development drilling. The planned production startup for Maria is in 2018. Recoverable reserves on the field are estimated around 180 million barrels of oil equivalent (boe), of which the majority is oil.

Under the approved development solution, the Maria reservoir will be linked via a subsea tieback to the Kristin, Heidrun and Åsgard B production platforms. The Maria well stream will go to the Kristin platform for processing while supply of water for injection into the reservoir will come from the Heidrun platform and lift gas will be provided from Åsgard B via the Tyrihans D field subsea template. Processed oil will be shipped to the Åsgard field for storage and offloading to shuttle tankers. Gas will be exported via the Åsgard Transport System to Kårstø.

Wintershall Norge is the operator of the license with a 50%* share. Petoro has a 30% share and Centrica Resources (Norge) owns the remaining 20%.

*Subject to approval by the relevant authorities and after closing of the transaction by the end of 2015, Tellus Petroleum will acquire 15% of the Maria development from Wintershall. 
 

Other news

3000 billion kroner from the SDFI since 2001
[11.03.2024] - Press Release Petoro 2023 results
3000 billion kroner from the SDFI since 2001
Read more
3000 billion kroner from the SDFI since 2001 - 2024-03-11 10:00
Continued strong cash flow despite lower gas prices and maintenance
[07.11.2023] - Press release - Third quarter 2023
Continued strong cash flow despite lower gas prices and maintenance
Read more
Continued strong cash flow despite lower gas prices and maintenance - 2023-11-07 10:00
Petoro delivered NOK 180 billion to the state in the first half of 2023
[02.08.2023] - Press release - Second quarter 2023
Petoro delivered NOK 180 billion to the state in the first half of 2023
Read more
Petoro delivered NOK 180 billion to the state in the first half of 2023 - 2023-08-02 10:00
Strong cash flow continues in the first quarter - Petoro delivered 117 billion to the State
[09.05.2023] - Press release - First quarter 2023
Strong cash flow continues in the first quarter - Petoro delivered 117 billion to the State
Read more
Strong cash flow continues in the first quarter - Petoro delivered 117 billion to the State - 2023-05-09 10:00
528 billion to the Norwegian state in 2022 - a year of exceptions
[14.03.2023] - Press Release Petoro 2022 results
528 billion to the Norwegian state in 2022 - a year of exceptions
Read more
528 billion to the Norwegian state in 2022 - a year of exceptions - 2023-03-14 10:00
New development plan for Snøhvit delivered
[21.12.2022]
New development plan for Snøhvit delivered
Read more
New development plan for Snøhvit delivered - 2022-12-21 14:00
Plan for Dvalin North gas field submitted
[13.12.2022]
Plan for Dvalin North gas field submitted
Read more
Plan for Dvalin North gas field submitted - 2022-12-13
Verdande secures important oil volumes for Norne
[03.12.2022]
Verdande secures important oil volumes for Norne
Read more
Verdande secures important oil volumes for Norne - 2022-12-06 11:00
Irpa in the Norwegian Sea will secure more gas to Europe
[22.11.2022]
Irpa in the Norwegian Sea will secure more gas to Europe
Read more
Irpa in the Norwegian Sea will secure more gas to Europe - 2022-11-22
PDO for Maria phase 2
[15.11.2022]
PDO for Maria phase 2
Read more
PDO for Maria phase 2 - 2022-11-15