Petoro pressing to keep profitable projects on track

SDFI in the nine months of 2009: NOK 77.5 billion
Even with relatively high crude prices over the past six months – averaging USD 68 per barrel in the third quarter – a number of oil companies on the Norwegian continental shelf are affected by great uncertainty and strict capital discipline.
A review of licences in which Petoro has holdings show that many developments are failing to keep to agreed timetables. The company is concerned that such delays could reduce long-term value creation, and aims to push for progress in profitable projects.
Income after financial items for the State’s Direct Financial Interest (SDFI) on the Norwegian continental shelf totalled NOK 75.2 million for the first nine months of 2009. That was down 34 per cent from the same period of 2008, which was a record year. Net cash flow to the government from the SDFI was NOK 77.5 billion for the first nine months and NOK 20.4 billion for the third quarter.

Daily production of oil and gas averaged 1 068 000 barrels of oil equivalent at 30 September. Gas output was up five per cent from last year, while production of oil and natural gas liquids fell by 10 per cent. Operating income for the first nine months was NOK 117.2 billion, compared with NOK 156.4 billion in the same period of last year.

Petoro has been pointing for the past year to the danger that market uncertainty might encourage short-term thinking by a number of operators. The company has noted that profitable projects are falling behind their approved schedules, in part because of stricter prioritisation of capital spending on the NCS. Delays could lead to a loss of business opportunities down the road and reduce value creation. It could also cut capacity and expertise in the supplies industry, threatening a new cost explosion when activity recovers. As the largest partner on the NCS, Petoro will press to ensure progress in profitable projects.

The justifications for delay can be complex, comments Kjell Pedersen, president and CEO of Petoro. They are often based on assessments of oil price uncertainties and the need for greater financial flexibility, achieved most easily by slowing investment. While acknowledging that such thinking could be appropriate for the individual oil company on the basis of its overall portfolio, Mr Pedersen believes that the total effect could be wrong for the NCS and the industry in Norway.

He points in this context to Statoil. “We’ve previously called attention to the special challenges posed by establishing such a dominant player. With the exception of exploration activity, the NCS is wholly dependent on the priorities determined by Statoil. Such a position creates many expectations. When Statoil sets particularly strict priorities for its capital spending, we expect profitable projects on the NCS to be given sufficient precedence and vigorously executed by comparison with other opportunities.”

Contact:
Sveinung Sletten, vice president external affairs, Petoro AS
Office phone: +47 51 50 20 24
Mobile: +47 95 07 55 54

Other news

High production and good cash flow in the first quarter
[02.05.2024] - Press release - First quarter 2024
High production and good cash flow in the first quarter
Read more
High production and good cash flow in the first quarter - 2024-05-02 10:00
3000 billion kroner from the SDFI since 2001
[11.03.2024] - Press Release Petoro 2023 results
3000 billion kroner from the SDFI since 2001
Read more
3000 billion kroner from the SDFI since 2001 - 2024-03-11 10:00
Continued strong cash flow despite lower gas prices and maintenance
[07.11.2023] - Press release - Third quarter 2023
Continued strong cash flow despite lower gas prices and maintenance
Read more
Continued strong cash flow despite lower gas prices and maintenance - 2023-11-07 10:00
Petoro delivered NOK 180 billion to the state in the first half of 2023
[02.08.2023] - Press release - Second quarter 2023
Petoro delivered NOK 180 billion to the state in the first half of 2023
Read more
Petoro delivered NOK 180 billion to the state in the first half of 2023 - 2023-08-02 10:00
Strong cash flow continues in the first quarter - Petoro delivered 117 billion to the State
[09.05.2023] - Press release - First quarter 2023
Strong cash flow continues in the first quarter - Petoro delivered 117 billion to the State
Read more
Strong cash flow continues in the first quarter - Petoro delivered 117 billion to the State - 2023-05-09 10:00
528 billion to the Norwegian state in 2022 - a year of exceptions
[14.03.2023] - Press Release Petoro 2022 results
528 billion to the Norwegian state in 2022 - a year of exceptions
Read more
528 billion to the Norwegian state in 2022 - a year of exceptions - 2023-03-14 10:00
New development plan for Snøhvit delivered
[21.12.2022]
New development plan for Snøhvit delivered
Read more
New development plan for Snøhvit delivered - 2022-12-21 14:00
Plan for Dvalin North gas field submitted
[13.12.2022]
Plan for Dvalin North gas field submitted
Read more
Plan for Dvalin North gas field submitted - 2022-12-13
Verdande secures important oil volumes for Norne
[03.12.2022]
Verdande secures important oil volumes for Norne
Read more
Verdande secures important oil volumes for Norne - 2022-12-06 11:00
Irpa in the Norwegian Sea will secure more gas to Europe
[22.11.2022]
Irpa in the Norwegian Sea will secure more gas to Europe
Read more
Irpa in the Norwegian Sea will secure more gas to Europe - 2022-11-22